Conveyance Project

Conveyance Project construction began in November 2018, with Project completion anticipated late 2020.

If you would like to sign up to receive Project updates, please contact the Community Liaison Officer by phone at 778-382-9011 or by email at NSCPsupport@kenaidan.com.

Conveyance Project Updates

In September 2019, the Project team issued the first edition of the Conveyance Project community newsletter, which can be viewed here. This edition includes community engagement to date, how the Conveyance Project relates to the overall North Shore Wastewater Treatment Plant Program, and a general update on Project activities. If you would like to sign up to receive the next edition, please email NSCPsupport@kenaidan.com.

First Narrows Pump Station

Construction of the pump station foundation and walls is underway. In August 2019, the Vancouver Fraser Port Authority approved an extension to work hours at the pump station site.

  • Extended work hours are in effect from 6 a.m. to midnight, Monday to Saturday through to February 2020.
  • No work will take place on Sundays or statutory holidays.
  • Completing this work during extended hours allows crews to safely and efficiently transport the concrete for large pours during off-peak traffic hours and maneuver equipment while no other activities are underway.

Pipe Alignment

Installation of Outfall Pipe: March 2019 – September 2020

The Project is using a combination of microtunneling, slip-lining, and open cut techniques for the installation of the outfall pipe (see outfall pipe alignment on map below). Microtunneling and slip-lining use a limited number of above-ground access points (shafts/trenches/etc.) to limit surface impacts.

  • Microtunneling is a self-contained system which reduces noise, dust and impacts to the environment and travelling public.
  • This method of ground improvement limits noise, while still creating the watertight structure required for microtunneling.
  • The new pipe will be tied into the existing outfall under the Lions Gate Bridge.

This work takes place during regular work hours of 7 a.m. to 8 p.m. Monday to Friday, and 9 a.m. to 5 p.m. on Saturday. No work takes place on Sundays or statutory holidays. Access to local business will be maintained.

Installation of Sewer Pipe: Deferred

The Project will use open cut installation for this component (locations C and D on map below).

  • Work will be completed in sections to minimize disruptions. Microtunneling is not suitable for this component as the pipe is smaller in diameter and there are many utilities in the area and connections are required.
  • Crews will remove sections of asphalt, lay down and connect the pipe, and replace the asphalt.
  • This work has been deferred to align with completion of the North Shore Wastewater Treatment Plant Project.
  • Advanced notification and information will be provided when this work commences.

Temporary lane closures

Work on West 1st Street (items A and B below) has been extended through to September 2020. The North Frontage Lane and Garden Avenue work (items C to E below) has been deferred to align with completion of the North Shore Wastewater Treatment Plant Project. More information will be provided in advance of this work. Please see map below for location details.

A) Eastbound West 1st Street west of Philip Ave. (March 2019 – September 2020)

  • One lane of traffic will be maintained in each direction
  • Pedestrians may be detoured to the south side of West 1st St.
  • Cyclists will share the road with vehicles

B)Eastbound West 1st Street west of Garden Ave (March 2019 – September 2020)

  • Local access only to this no exit block

C) North Frontage Lane (Deferred)

  • Alternate access to local businesses from Welch St. via Garden Ave. and Philip Ave.
  • Temporarily close north parking lane and bicycle lane – cyclists will share the road with vehicles.

D) & E) Full Closure of the intersection of Garden Ave. at West 1st St. to install pipes (Deferred)

  • Detour for cyclists and vehicles via Philip Ave. and Welch St.
  • Access to local businesses will be maintained

Project Overview

The Lions Gate Wastewater Treatment Plant, situated just to the west of the Lions Gate Bridge, serves the North Shore municipalities of West Vancouver, the City of North Vancouver, the District of North Vancouver, and Squamish Nation. The plant is one of two remaining primary treatment plants in the region.

New federal regulations require all primary treatment plants be upgraded to secondary treatment by December 31, 2020. Secondary treatment is a biological process that uses aerobic bacteria to consume suspended solids and dissolved organic materials in wastewater. Secondary treatment plants remove about 95 per cent of the organic materials in wastewater. The new facility will provide a higher level of treatment to the North Shore’s wastewater before it is sent into Burrard Inlet.

In July 2018, Metro Vancouver awarded the North Shore Conveyance Partners (NSCP) the contract to design and construct a pump station and related pipes to convey wastewater from the existing Lions Gate Wastewater Treatment Plant to the new North Shore Wastewater Treatment Plant  that is currently under construction on West 1st Street between Pemberton Avenue and Philip Avenue.

The new First Narrows Pump Station will be located near the existing Lions Gate Wastewater Treatment Plant. The pipe alignment will extend from the existing outfall under the Lions Gate Bridge to the new North Shore Wastewater Treatment Plant. The Conveyance Project includes the following components:

  • Constructing a new pump station located at south end of Bridge Road underneath the Lions Gate Bridge
  • Installing a 1200 mm influent sewer pipe extending from the existing Lions Gate Wastewater Treatment Plant to the new pump station
  • Installing a 900 mm forcemain extending from the new pump station to the new North Shore Wastewater Treatment Plant
  • Installing a 2100 mm effluent sewer pipe extending from the new North Shore Wastewater Treatment Plant to the existing outfall

With plant construction underway, the Conveyance Project represents the next step in the overall North Shore Wastewater Treatment Plant program. The final step, decommissioning the existing Lions Gate Wastewater Treatment Plant, will begin in the mid-2020s and the land returned to Squamish Nation.

To review the permit application with the Vancouver Fraser Port Authority, visit here.

Infrastructure Map

Engagement Overview

A public open house was held on October 25, 2018 and the feedback period on construction mitigation is closed. See the Open House Display Boards for project information.

 Conveyance Project Engagement Summary – Jan 2019