Overview of Projects


Metro Vancouver is building the North Shore Wastewater Treatment Plant, a new treatment facility that will provide tertiary treatment to better protect the environment. 

The program includes:

  • The North Shore Wastewater Treatment Plant Project
    See below for project updates

  • The pump station and sewer pipes to serve the new plant (the Conveyance Project)
    Learn more about the Conveyance Project
  • Decommissioning the existing Lions Gate Wastewater Treatment Plant
    This work will begin in the mid-2020s. When complete, the land will be returned to Squamish Nation.

About the Treatment Plant

The North Shore Wastewater Treatment Plant is a new tertiary treatment facility being built to replace the existing primary level Lions Gate Wastewater Treatment Plant on the North Shore. Tertiary treatment exceeds federal regulatory requirements for treatment technology and will ensure the treated wastewater released into the marine environment is much cleaner.

The new treatment plant is being built to serve 250,000 residents and businesses in the Districts of West and North Vancouver, the City of North Vancouver, and the Squamish and Tsleil‑Waututh Nations and will:

  • Improve the quality of the treated wastewater released into the Burrard Inlet
  • Feature a modern, enclosed design and robust odour control system to prevent odour from reaching neighbouring residents and businesses
  • Recover heat for use by the Lonsdale Energy Corporation as an alternative energy source
  • Be constructed to Leadership in Energy and Environmental Design (LEED) Gold and ENVISION Gold certification standards
  • Include a public plaza, education and community meeting spaces

  Location: West 1st Street, between Pemberton Avenue and Philip Avenue, District of North Vancouver

March 2023 Project Status Update

In spring 2022, PCL became the new construction manager for the project and took over the treatment plant site. AECOM took over the role of design consultant for the project around the same time.

Metro Vancouver is working collaboratively with PCL and AECOM to develop a plan to complete the project as quickly as possible, while considering the best interests of the region.

We are currently working to identify and correct numerous design and construction errors and deficiencies from the previous contractor, who was responsible for both designing and building the new treatment plant. These design and construction issues must be addressed to develop an accurate project schedule and cost estimate so construction can move forward. We expect to present an updated cost estimate and schedule to Metro Vancouver’s Board of Directors for consideration in mid-2023.

Updates will be provided as new information becomes available. We look forward to the successful completion of a tertiary treatment plant that meets and exceeds safety and regulatory requirements.

Current Activity at the Treatment Plant Site

PCL will continue early works construction at the treatment plant site through mid-2023.

What to expect on and near the site over the coming month:

  • Crews installing rebar and pouring concrete
  • Crews repairing concrete deficiencies on existing structures
  • Construction noise from power tools and equipment
  • Cranes moving materials and equipment
  • Excavators working inside the site fence line
  • Vehicles delivering materials to the site via West 1st Street, between Pemberton Avenue and Philip Avenue
  • Crews conducting minor road maintenance as needed on West 1st Street

  • Project Documents

    Email Newsletters

    From April 2022 onwards, we will provide the community with updates about the project and site activities approximately once a month through an email newsletter. You can sign up to the mailing list by clicking the button under “Stay Connected”.

    Project Fact Sheets

    Media Releases

    Reports

    • May 17, 2023
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • April 12, 2023
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • March 15, 2023
      Liquid Waste Committee: North Shore Wastewater Treatment Plant Project Early Works Agreement Extension
       Report
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • February 8, 2023
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • October 5, 2022
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • September 21, 2022
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • July 13, 2022
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • June 8, 2022
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • May 18, 2022
      North Shore Wastewater Treatment Plant Project Update in Liquid Waste Committee Manager’s Report
       Report
    • April 13, 2022
      Liquid Waste Committee: North Shore Wastewater Treatment Plant Project Update
       Report
       Presentation
    • March 9, 2022
      Liquid Waste Committee: Contract Amendment of RFP No. 14-205 - Design Build Consulting Services for the Lions Gate Secondary Wastewater Treatment Plant to Design Consultant, Engineer of Record Service
       Report
    • February 23, 2022
      Liquid Waste Committee: Award of Contract Resulting from RFQ No. 21-457: North Shore Wastewater Treatment Plant (NSWWTP) Project
       Report
       Presentation
  • Construction Impacts

    Construction impacts for the North Shore Wastewater Treatment Plant project may include:

    • Traffic pattern changes and possible temporary delays
    • Parking restrictions
    • Large vehicles and heavy equipment in the work area and on nearby roads
    • Construction noise and vibration
  • Work Hours

    Monday to Friday between 7:00 am and 8:00 pm

    Saturdays between 9:00 am and 5:00 pm

    All work will comply with District of North Vancouver bylaws or granted bylaw variances. Advance notification will be provided if extended working hours are scheduled.

  • Sustainability

    The new treatment plant will be constructed to the Leadership in Energy and Environmental Design (LEED) Gold and ENVISION Gold certification standards. The plant will harvest and reuse rainwater outside the plant and will conserve and reclaim water used within the plant.

    What is LEED? Leadership in Energy and Environmental Design (LEED) is one of the most popular green building certification programs used worldwide. LEED seeks to optimize the use of natural resources, promote regenerative and restorative strategies, maximize the positive and minimize the negative environmental and human health consequences of the construction industry, and provide high-quality indoor environments for building occupants.

    What is ENVISION? Envision® is a sustainability rating system and planning guide for introducing sustainability considerations into infrastructure projects. Envision assesses not only individual project performance, but how well projects contribute to the efficiency and long-term sustainability of the communities they serve.

    Both rating systems are complementary and provide a flexible framework to identify sustainable approaches throughout Project design, construction and plant operations.

  • Working with the Community

    Metro Vancouver is committed to minimizing impacts and working with the community to listen to concerns and interests and ensure they are considered as the project progresses. A community liaison is available to address issues, answer questions from the community, and provide project updates as they arise.

    We have worked closely with North Shore communities, special interest groups, local governments and First Nations since 2012 to learn about their values, interests and concerns. This engagement informed the design of the new wastewater treatment plant. You can find meeting summaries and past presentations here:

 Maps & Images

About the Conveyance Project

A pump station and new pipes are needed to move wastewater from West Vancouver to the new North Shore Wastewater Treatment Plant, and to move the treated wastewater from the new plant to the existing outfall, located under the Lions Gate Bridge. Construction of the pump station and a large portion of the conveyance piping was completed in summer 2022. The remaining pipes will be installed when construction of the new treatment plant is nearing completion.

Funding Partners

The Federal and Provincial governments are providing joint funding of up to $405 million toward the construction of the North Shore Wastewater Treatment Plant. For more information on federal infrastructure funding, visit: www.infrastructure.gc.ca.

Timeline

 

 

Jan 2012 – Dec 2013False1Jan 2012 – Dec 2013<div class="ExternalClassEACCEB319CC2462CA5DA4DF887D3104A"><p>​Project Definition<br></p></div>
2014 – 2024True22014 – 2024<div class="ExternalClassBF2921C0A30645CAA5A4D1F26F74E293"><p>​Design & Construction<br></p> </div>
2024False32024<div class="ExternalClass916BDEB325004FAA92E0267035CBF67E"><p>​Plant Operational<br></p></div>


Stay Connected


Subscribe to our mailing list to receive e-newsletters about our Liquid Waste engagement projects

Sign up

Community Liaison

A Community Liaison is working with local residents and businesses to address any concerns throughout construction.

Phone: 604-639-9012

nswwtp@metrovancouver.org


Metro Vancouver Information Centre

Phone: 604-432-6200 (Monday to Friday from 8:00 am to 4:30 pm)

After-Hours Emergency Line: 604-451-6610